1.

The number of function points of a proposed system is calculated as 500. Suppose that the system is planned to be developed in Java and the LOC/FP ratio of Java is 50. Estimate the effort (E) required to complete the project using the effort formula of basicCOCOMO given below:E = a(KLOC)bAssume that the values of a and b are 2.5 and 1.0 respectively.

A. 25 person months
B. 75 person months
C. 62.5 person months
D. 72.5 person months
Answer» D. 72.5 person months