The latest finish time for an activity: |
| A. | Equals the min. of LFT − t for all immediate successors |
| B. | Equals the max. of LFT − t for all immediate predecessors. |
| C. | Equals the max. of EST + t for all immediate predecessors. |
| D. | Equals the min. of EST + t for all immediate successors. |
| Answer» B. Equals the max. of LFT − t for all immediate predecessors. | |