| 1. |
The estimate of shortest possible time when the works can be completed under ideal conditions is called |
| A. | optimum time estimate |
| B. | Most likely time estimate |
| C. | Pessimistic time estimate |
| D. | minimum time estimate |
| Answer» B. Most likely time estimate | |