The essential condition for the decompression of an activity is that |
| A. | The project time should change due to decompression |
| B. | After decompression the time of an activity invariably exceeds its normal time |
| C. | An activity could be decompressed to the maximum extent of its normal time |
| D. | None of the above |
| Answer» D. None of the above | |