The efficiency of B is twice that of A. A can do a work in 15 days. B joins the work a few days after A starts work. They completed that work in 11 days from the beginning. How many days did they work together? |
| A. | 6 days |
| B. | 1 days |
| C. | 5 days |
| D. | 2 days |
| Answer» E. | |