| 1. |
The digging work of the DMRC on the Adohini-Andheriamore stretch requires Twenty-four men to complete the work in sixteen days. As a part of the task if DMRC were to hire Thirty-two women, they can complete the same work in twenty-four days. Sixteen men and sixteen women started working and worked for twelve days. Due to time bound schedule the work had to be completed in remaining 2 days, for which how many more men are to be employed? |
| A. | 48 |
| B. | 24 |
| C. | 36 |
| D. | 16 |
| Answer» C. 36 | |