The difference between costs linked to highest and lowest observation of cost driver is $8000 and observation of cost driver is 40 machine hours then slope coefficient is |
| A. | $16,000 |
| B. | $200 |
| C. | $400 |
| D. | $20,000 |
| Answer» C. $400 | |