| 1. |
The critical jobs are: A, D, H, and I. What is the standard deviation of the project duration?Job A B C D E F G H IStandard deviation 1 4 0 1 0 1 2 1 1 |
| A. | 2 |
| B. | 1 |
| C. | 4 |
| D. | √ 11 |
| Answer» B. 1 | |