| 1. |
The correct sequence of operations in production planning and control is |
| A. | Routing-Scheduling-Dispatching-Follow up |
| B. | Scheduling-Routing- Dispatching-Follow up |
| C. | Dispatching-Routing-Scheduling- Follow up |
| D. | Routing-Scheduling-Follow up-Dispatching |
| Answer» B. Scheduling-Routing- Dispatching-Follow up | |