The correct sequence of drilling equipment for increasing size of holes in tunnels is________________? |
| A. | wagon drill, churn drill, shot drill |
| B. | wagon drill, shot drill, churn drill |
| C. | shot drill, churn drill, wagon drill |
| D. | churn drill, wagon drill, shot drill |
| Answer» B. wagon drill, shot drill, churn drill | |