The activity-on-arrow network of activities for a construction project is shown in the figure. Thedurations (expressed in days) of the activities are mentioned below the arrows.The critical duration for this construction project is

A. 13 days
B. 14 days
C. 15 days
D. 16 days
Answer» D. 16 days