The activity-on-arrow network of activities for a construction project is shown in the figure. Thedurations (expressed in days) of the activities are mentioned below the arrows.The critical duration for this construction project is |
| A. | 13 days |
| B. | 14 days |
| C. | 15 days |
| D. | 16 days |
| Answer» D. 16 days | |