Sumit and Amit undertook a work for Rs 7200. Sumit alone can do the work in 5 days and Amit alone can do the work in 4 days. If they work together, then what will be the difference (in Rs.) in the amount they receive?

A. 800
B. 1600
C. 1200
D. 1400
Answer» B. 1600