Statement (I): In resource levelling, project completion time is not extended provided there is no constraint on availability of resources.Statement (II): There is generally a constraint against exceeding the project duration time.

A. Both Statement (I) and Statement (II) are individually true and Statement (II) is the correct explanation of Statement (I)
B. Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)
C. Statement (I) is true but Statement (II) is false
D. Statement (I) is false but Statement (II) is true
Answer» B. Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)