1.

Statement (I): In a multipath PERT network, the project duration resulting from the critical path always has a 50% probability of completion by that duration.Statement (II): The expected - path duration together with 3-times the standard deviation of that expected duration must be considered for all the paths in the network.

A. Both Statement (I) and Statement (II) are individually true and Statement (II) is the correct explanation of Statement (I)
B. Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)
C. Statement (I) is true but Statement (II) is false
D. Statement (I) is false but Statement (II) is true
Answer» D. Statement (I) is false but Statement (II) is true