| 1. |
Statement (I): Crashing of project duration always increases the cost of the project on its completion, no matter what the indirect, or overhead, costs are.Statement (II): The critical path along the project activities network diagram is compressed in the process of investigating the crashing of the project duration, and not the non-critical activities, up to a certain stage of crashing. |
| A. | Both Statement (I) an Statement (II) are individually true and Statement (II) is the correct explanation of Statement (I) |
| B. | Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I) |
| C. | Statement (I) is true but Statement (II) is false |
| D. | Statement (I) is false but Statement (II) is true |
| Answer» E. | |