1.

Software Cost Performance index (CPI) is given by:(Where:   BCWP stands for Budgeted Cost of Work PerformedBCWS stands for Budget Cost of Work ScheduledACWP stands for Actual Cost of Work Performed)

A. BCWP/ACWP
B. BCWP−ACWP
C. BCWP−BCWS
D. None of the above
Answer» B. BCWP−ACWP