Six jobs arrived in a sequence as given below:JobsProcessing Time (days)I4II9III5IV10V6VI8Average flow time (in days) for the above jobs using Shortest Processing Time rule is |
| A. | 20.83 |
| B. | 23.16 |
| C. | 125 |
| D. | 139 |
| Answer» B. 23.16 | |