Q: A can do a work in 24 days and B is 20% more efficient than A. If C can do the work in 10 days more than B, then find the days taken by A and C together to complete the work. |
| A. | 15 days |
| B. | 13 days |
| C. | 12 days |
| D. | 18 days |
| E. | None of these |
| Answer» C. 12 days | |