Q: A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C they can finish it in 5 days. If they are paid ₹ 960 for the whole work. How much money A gets? |
| A. | 320 |
| B. | 400 |
| C. | 480 |
| D. | 240 |
| Answer» C. 480 | |