| 1. |
Q: A, B , C can finish a work in 10, 12, and 15 days respectively. They start working together. If B stops after 2 days, how long would it take A and C to finish the remaining work |
| A. | 3 days |
| B. | $$ {3{8\over 11}}\ days$$ |
| C. | $$ {2{6\over 11}}\ days$$ |
| D. | $$ {3{6\over 11}}\ days$$ |
| Answer» B. $$ {3{8\over 11}}\ days$$ | |