Q: A, B and C can do a work in 6, 12 and 24 days respectively. In what time will they finish the work while working together? |
| A. | $$ 3 {3\over7} $$days |
| B. | $$ 2 {3\over7} $$days |
| C. | $$ 4 {3\over7} $$days |
| D. | $$ 3 {3\over5} $$days |
| Answer» B. $$ 2 {3\over7} $$days | |