MCQOPTIONS
Saved Bookmarks
| 1. |
Pick up the PERT event from the following: |
| A. | none of these. |
| B. | Digging of foundation started |
| C. | Digging of foundation completed |
| D. | Laying of concrete started |
| Answer» E. | |