Pick up the correct statement from the following:$? |
| A. | The difference of latest occurrence time and earliest expected time, is called slack |
| B. | The activities connecting the events having zero slack, lie on the critical path |
| C. | The critical path consumes the maximum time |
| D. | All the above |
| Answer» E. | |