MCQOPTIONS
Saved Bookmarks
| 1. |
Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following: |
| A. | all the above. |
| B. | Pouring of Concrete 2. Erection of form work 3. Curing of concrete 4. Removal of form work |
| C. | Erection of form work 2. Pouring of concrete 3. Curing of concrete 4. Removal of form work |
| D. | Removal of form work 2. Erection of form work 3. Pouring of concrete 4. Curing of concrete |
| Answer» C. Erection of form work 2. Pouring of concrete 3. Curing of concrete 4. Removal of form work | |