MCQOPTIONS
Saved Bookmarks
| 1. |
Phase in which task scheduling is accomplished and is essential because multiple software teams work in parallel on different system functions is |
| A. | communication |
| B. | planning |
| C. | construction |
| D. | deployment |
| Answer» C. construction | |