| 1. |
P, Q and R take 18, 15 and 10 days respectively to complete a job. Compare their efficiencies as a ratio. |
| A. | 5 : 6 : 9 |
| B. | 5 : 5 : 9 |
| C. | 5 : 6 : 4 |
| D. | 5 : 6 : 10 |
| Answer» B. 5 : 5 : 9 | |