P, Q and R can complete a piece of work in 45, 15 and 5 days respectively. In how may days all three together can complete the same work? |
| A. | 45/14 |
| B. | 45/13 |
| C. | 9/2 |
| D. | 11/2 |
| Answer» C. 9/2 | |