P can do a piece of work in 20 days and Q can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 21 days. In how many days will R alone finish the whole work? |
| A. | 30 |
| B. | 33 |
| C. | 36 |
| D. | 42 |
| Answer» D. 42 | |