P and Q together can complete a work in 105 days. Q and R together can complete the same work in 90 days, P and R together can complete the same work in 126 days. In how many days P, Q and R together can complete the same work? |
| A. | 70 days |
| B. | 74 days |
| C. | 76 days |
| D. | 72 days |
| Answer» B. 74 days | |