P and Q can do some work individually in 8 and 16 days respectively. They work together and completed the work. What is the ratio of work done by P and Q, when the work was completed? |
| A. | 2 : 1 |
| B. | 3 : 2 |
| C. | 2 : 3 |
| D. | 2 : 5 |
| Answer» B. 3 : 2 | |