MCQOPTIONS
Saved Bookmarks
| 1. |
On an activity diagram, which of the following is not a valid use of a synchronization bar? |
| A. | to initiate the alternative paths. |
| B. | 1 |
| C. | 2 |
| D. | 3 |
| Answer» B. 1 | |