| 1. |
Mohan can do a bit of work in 25 days which can be completed by Sohan in 20 days. Both together labour for 5 days and afterward Mohan leaves off. How long will Sohan take to complete the remaining work ? |
| A. | 20 days |
| B. | 11 days |
| C. | 14 days |
| D. | 21 days |
| E. | None of the above/More than one of the above |
| Answer» C. 14 days | |