Let ‘x’ be the number of days taken by B alone to finish the whole work Then, A alone will finish the whole work in 3x/4 × 2 days = 3x/2 days. Then, working together, 3x/2 × x/3x/2 + |
| A. | 30 days |
| B. | 35 days |
| C. | 40 days |
| D. | 45 days |
| Answer» B. 35 days | |