Labour rate variance is computed by multiplying the |
| A. | Standard labour rate with the difference between standard labour hours and actual labour hours |
| B. | Actual labour hours with the difference between standard labour hours and actual labour hours |
| C. | Actual labour rate with the difference between standard labour rate and actual labour hours. |
| D. | None of the above |
| Answer» E. | |