MCQOPTIONS
Saved Bookmarks
| 1. |
In a PERT/CPM network, computing the critical path requires |
| A. | determining the total project duration |
| B. | assigning the earliest finish time for an activity as the earliest start time for the next |
| C. | that the latest finishing time for an activity not delay the overall project beyond initial expectation |
| D. | a sophisticated and complex computer program |
| Answer» C. that the latest finishing time for an activity not delay the overall project beyond initial expectation | |