If the budgeted total direct labor hours are 3800 and budgeted direct labor cost is $480000, then the budgeted direct labor cost rate will be |
| A. | $126.32 per labor hour |
| B. | $128.32 per labor hour |
| C. | $130 per labor hour |
| D. | $132 per labor hour |
| Answer» B. $128.32 per labor hour | |