If re-ordering level is 450 units while consumption of materials are 25-27 units and materials are received within 4-6 weeks, the minimum level will be |
| A. | 100 units |
| B. | 200 units |
| C. | 150 units |
| D. | 250 units |
| Answer» C. 150 units | |