| 1. |
*/*_If flexible budget variance is $105000, actual cost is $65000 then flexible budget cost will be? |
| A. | $40,000 |
| B. | $50,000 |
| C. | $150,000 |
| D. | $170,000 |
| Answer» B. $50,000 | |