If budgeted total direct labour hours are 5500 and budgeted direct labour cost is $755000, then budgeted direct labour cost rate is |
| A. | 138 per labour hour |
| B. | 137.27 per hour |
| C. | 140 per labour hour |
| D. | 142 per labour hour |
| Answer» C. 140 per labour hour | |