If budgeted price of input is $70, actual quantity of input is 250 units and allowed budgeted quantity of input is 90 units, then efficiency variance will be |
| A. | 23,800 |
| B. | 11,200 |
| C. | 12,200 |
| D. | 13,200 |
| Answer» C. 12,200 | |