_ If an actual price of material is $700 and budgeted price is $900, then the$? |
| A. | cost variance is favourable |
| B. | cost variance is unfavourable |
| C. | price variance is favourable |
| D. | price variance is unfavourable |
| Answer» D. price variance is unfavourable | |