If 9 men working 71/2 hours a day can finish a piece of work in 20 days, then how many days will be taken by 12 men, working 6 hours a day to finish the work? It is being given that 2 men oflatter type work as much as 3 men of the former type? |
| A. | 91/2 |
| B. | 11 |
| C. | 121/2 |
| D. | 13 |
| Answer» D. 13 | |