If 80 persons can finish a work within 16 days by working 6 hours a day, the number of hours a day, should 64 persons work to finish that very job within 15 days is :

A. 5 hrs.
B. 7 hrs.
C. 8 hrs.
D. 6 hrs.
Answer» D. 6 hrs.