| 1. |
If 6 men or 8 children complete one task in 24 days, then how many days will be required to complete the task for 7 men and 12 children ? |
| A. | 12 |
| B. | 9 |
| C. | 10 |
| D. | 16 |
| Answer» C. 10 | |