If 27 people, working 8 hours a day, can complete a task in 12 days, then in how many days will 18 people finish the task, working 9 hours a day? |
| A. | 18 days |
| B. | 16 days |
| C. | 20 days |
| D. | 15 days |
| Answer» C. 20 days | |