Saved Bookmarks
| 1. |
If 10 unskilled workers finish a job in 4 days, how many skilled workers should be hired, who are twice efficient than unskilled workers to finish the job in 2 days. |
| A. | 2 |
| B. | 12 |
| C. | 10 |
| D. | 5 |
| Answer» D. 5 | |