MCQOPTIONS
Saved Bookmarks
| 1. |
i. 4 men and 6 boys can finish a job in 8 days. ii. 3 men and 7 boys take 10 days to complete the same job. In how many days will 10 boys complete the job? |
| A. | 35 |
| B. | 40 |
| C. | 45 |
| D. | 50 |
| Answer» C. 45 | |