1.

Given standard time per unit is 80 hours, standard time per hour @ Rs 1 per hour, actual time per unit is 90 hours and actual rate per hour @ Rs 1.10 per hour. Determine labour cost variance, labour rate variance and labour efficiency variance.

A. Rs 11, Rs 22 and Rs 10 all unfavorable
B. Rs 19, Rs 9 and Rs 10 all favorable
C. Rs 19, Rs 9 and Rs 10 all unfavorable
D. Rs 11, Rs 22 and Rs 10 all favorable
Answer» D. Rs 11, Rs 22 and Rs 10 all favorable