For butt welding 40 mm thick steel plates, when the expected quantity of such jobs is 5000 per month over a period of 10 years, choose the best suitable welding process out of the following available alternatives. |
| A. | SAW |
| B. | Oxyacetylene gas welding |
| C. | EBM |
| D. | MIG |
| Answer» B. Oxyacetylene gas welding | |