MCQOPTIONS
Saved Bookmarks
| 1. |
For a company with an average daily demand of 9 units and a standard deviation of 3 units, a 9-day lead time, and a 95% service level, which of the following statements is true? |
| A. | The reorder point is about 81 units |
| B. | The safety stock is about 15 units |
| C. | The reorder point is about 96 days. |
| D. | The-reorder point is about. 81 days |
| Answer» B. The safety stock is about 15 units | |